Initial Scan – 10/12/19
Progress Scan – 12/19/19
Grand Opening Scan – 03/06/20
- Pipeline Setup
- VPO: Sabrina Sennett
- RDO: Lori Schoenberger
- RSA: Todd Summersell
- RMO: Kat Ladniak
- PMO: Kimberly Boudreaux
- DNI: Eleanor Deselm
- Setup: Darlene Solis 1/27-1/31
- Carestream: 2/3/2020
- HDDO: 1/21/2020
- Pipeline Status
- Pano Installation Date: 1/29/20
- In-Service Training Day: 1/31/20
- Kavo Pano Training Date: 2/3/20
- USPS Verified
- GC to establish utilities
- Water -need proof of ownership
- Gas – transfer requested
- Electric – In HD name
- HD signed and sent lease
- Letter from LL, delivery expected for 11/5
- E.D. 8/1/2019
- O.D. 10/1/2019